Phase2 Iteration5
The Phase 2 works in iterations. See setup of the Architecture stream.
Contents
Iteration 5
The fifth iteration lasts from 25.March to 15.April.
Topics
Capabilities
There are two new topics to handle:
C43: Office Integration of RSDS requests
The task foresees to lower the hurdles for A type RUs to access RollingStock datasets. This should be achieved by utilizing Office technology.
C14: Define report tool for RFF
The target is to define the centrally operated reporting tool for the RFF digital platform.
And three existing to continue:
C01: Managed CRD Location Masterdata
The target of this task is to enhance the CRD masterdata to a level where it can be used as new GEO masterdata reference. We will start this task in this iteration by
- collect the experience and gaps with the CRD data quality so far
- sketch a analysis method to determine the actual state of the master data
- evaluate whether a data quality assurance is needed (CRD KPI)
- defining the maintenance process
We know that this task will accompany us for several iterations.
SM: SmartService Profile
Based on the Smart Services list we continue to describe the Smart Services. With these profiles we can then start the discussion with the CIO/steering committee on prioritization.
Reviews
Smart Service profiles
- SM_08 Siding Everywhere
- SM_17 Facilities on location
- SM_24 Authority Communication