Difference between revisions of "Phase2 Iteration1"
From RFF Wiki
Line 8: | Line 8: | ||
## C14 Monitor WSM data quality | ## C14 Monitor WSM data quality | ||
## C34 Monitor WPM data quality | ## C34 Monitor WPM data quality | ||
− | ## C19 | + | ## C19 Train operation for small RU |
## C77 Consignment note for small RU | ## C77 Consignment note for small RU | ||
# Plan iterations 2 to 4 | # Plan iterations 2 to 4 | ||
# Prepare ticket system | # Prepare ticket system | ||
=== Results === | === Results === | ||
+ | ==== C14 Monitor WSM ==== | ||
+ | In this iteration we worked out four steps to monitor the WSM data quality and coverage. | ||
+ | * Identified WSM KPIs | ||
+ | * Defined measurement points | ||
+ | * Prioritized KPIs | ||
+ | * Roadmap KPIs | ||
+ | |||
+ | The first step focus on identification of the KPIs to be measured. | ||
+ | |||
+ | ==== C34 Monitor WPM ==== | ||
+ | ==== C19 Train Operation ==== | ||
+ | ==== C77 Consignment Note in WDI ==== |
Revision as of 08:54, 4 February 2021
The Phase2 works in iterations.
Contents
Iteration 1
The first iteration lasts from 21.January to 11.February.
Topics
- Capabilities
- C14 Monitor WSM data quality
- C34 Monitor WPM data quality
- C19 Train operation for small RU
- C77 Consignment note for small RU
- Plan iterations 2 to 4
- Prepare ticket system
Results
C14 Monitor WSM
In this iteration we worked out four steps to monitor the WSM data quality and coverage.
- Identified WSM KPIs
- Defined measurement points
- Prioritized KPIs
- Roadmap KPIs
The first step focus on identification of the KPIs to be measured.