Difference between revisions of "Phase3 Iteration7"
From RFF Wiki
(2 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | = Iteration | + | = Iteration 22.7 = |
The iteration lasts from 21.June to 12.July. | The iteration lasts from 21.June to 12.July. | ||
= Topics = | = Topics = | ||
− | |||
* WP workshops status | * WP workshops status | ||
− | |||
* Planning 2022 | * Planning 2022 | ||
Line 13: | Line 11: | ||
# [[Digital Train Operations]] Initial Workshop on 8.June √ | # [[Digital Train Operations]] Initial Workshop on 8.June √ | ||
# [[Digital Train Handover]] Initial Workshop on 9.June √ | # [[Digital Train Handover]] Initial Workshop on 9.June √ | ||
− | # [[Digital Consignment Note]] Initial Workshop on 5.July | + | # [[Digital Consignment Note]] Initial Workshop on 5.July √ |
− | # [[Digital Train Composition]] Initial Workshop on 30.June | + | # [[Digital Train Composition]] Initial Workshop on 30.June √ |
# [[Telematic Data Sharing]] Initial Workshop on 13.June √ | # [[Telematic Data Sharing]] Initial Workshop on 13.June √ | ||
# [[Train Service Harmonization]] Initial Workshop on 14.June √ | # [[Train Service Harmonization]] Initial Workshop on 14.June √ | ||
− | # [[Train ETA Service]] Initial Workshop on 27.June | + | # [[Train ETA Service]] Initial Workshop on 27.June √ |
The DP Rail organisation is laid out here: | The DP Rail organisation is laid out here: | ||
Line 27: | Line 25: | ||
* June/July: | * June/July: | ||
** Business Workshops | ** Business Workshops | ||
− | ** | + | * August/September: |
− | * | + | ** Replanning workpackages |
** Technical Workshops | ** Technical Workshops | ||
+ | * October/November: | ||
** Workpackage leader introduction | ** Workpackage leader introduction | ||
− | |||
** Finalization of Dossiers | ** Finalization of Dossiers | ||
− | |||
** KickOff of the Workpackages | ** KickOff of the Workpackages | ||
+ | |||
+ | == Next iteration == | ||
+ | The next iteration will be a long one, with a duration of 6 weeks, over the summer break. | ||
+ | It will last from 12.July to 23.August. | ||
+ | |||
+ | == CEF answer == | ||
+ | With the decline on the CEF call 2022 we need to replan our steps and how we will continue in 2022/2023. | ||
+ | # inform the community (see mail from Tibo) | ||
+ | ## we continue | ||
+ | ## we replan | ||
+ | ## new planning available in October | ||
+ | |||
+ | # adapt the organisation | ||
+ | # focus our work in the workpackages | ||
+ | # prepare CEF call 2023 | ||
+ | |||
+ | === Organisation === | ||
+ | * Consolidation | ||
+ | * Restructuring/Shrinking work packages | ||
+ | |||
+ | === Workpackages === | ||
+ | Based on the evaluation we have carried out in the business workshops we will select from the topics those that | ||
+ | * concern the basics, | ||
+ | * address the business processes (rules, data structures) and | ||
+ | * generate a large benefit (with a small IT investment) | ||
+ | |||
+ | So we will concentrate our work on | ||
+ | * Data quality | ||
+ | * Governance | ||
+ | * small IT services (e.g improvements in MARS, add on's to existing services like ISR, ORFEUS) | ||
+ | |||
+ | === CEF funding === | ||
+ | To participate in the CEF call 2023 we start the preparation after the summer break. | ||
+ | * experience from the call 2022 | ||
+ | * learn from other participants | ||
+ | * look for assistance/knowledge |
Latest revision as of 09:10, 22 August 2022
Contents
Iteration 22.7
The iteration lasts from 21.June to 12.July.
Topics
- WP workshops status
- Planning 2022
DP Rail topics
In DP Rail the following topics are treated:
- Digital Train Operations Initial Workshop on 8.June √
- Digital Train Handover Initial Workshop on 9.June √
- Digital Consignment Note Initial Workshop on 5.July √
- Digital Train Composition Initial Workshop on 30.June √
- Telematic Data Sharing Initial Workshop on 13.June √
- Train Service Harmonization Initial Workshop on 14.June √
- Train ETA Service Initial Workshop on 27.June √
The DP Rail organisation is laid out here: File:DP-RAIL-Contribution RFF IT Fullteam Folien 0-19.pdf
In the meantime the SteerCo has validated the proposed RFF organisation setup.
Planning 2022
- June/July:
- Business Workshops
- August/September:
- Replanning workpackages
- Technical Workshops
- October/November:
- Workpackage leader introduction
- Finalization of Dossiers
- KickOff of the Workpackages
Next iteration
The next iteration will be a long one, with a duration of 6 weeks, over the summer break. It will last from 12.July to 23.August.
CEF answer
With the decline on the CEF call 2022 we need to replan our steps and how we will continue in 2022/2023.
- inform the community (see mail from Tibo)
- we continue
- we replan
- new planning available in October
- adapt the organisation
- focus our work in the workpackages
- prepare CEF call 2023
Organisation
- Consolidation
- Restructuring/Shrinking work packages
Workpackages
Based on the evaluation we have carried out in the business workshops we will select from the topics those that
- concern the basics,
- address the business processes (rules, data structures) and
- generate a large benefit (with a small IT investment)
So we will concentrate our work on
- Data quality
- Governance
- small IT services (e.g improvements in MARS, add on's to existing services like ISR, ORFEUS)
CEF funding
To participate in the CEF call 2023 we start the preparation after the summer break.
- experience from the call 2022
- learn from other participants
- look for assistance/knowledge